Site Diary

Daily reports from every site — who was working, what got done, and what is blocking progress

Manpower on site today
378
2 sites reported
Equipment deployed
6
Cranes, pumps, lifts
Open site issues
3
Raised in daily reports
Progress photos
40
This week

Al Noor Residential Tower · 25 Sept 2026

Sunny, humid, 39°C
Carpenters 42Steel fixers 36Masons 18MEP 24Helpers 55Total 175
Work done
  • L26 slab reinforcement 80% complete
  • Blockwork L14–L15 ongoing
  • Façade bracket installation east elevation
Concrete pour L26 moved to Saturday 5 am — midday heat restriction
Equipment: Tower crane TC-02, Concrete pump 42m, 2 × boom liftsVisitors: Consultant RE — slab inspection14 photos · Site Engineer — Al Noor

Dubai Marina Mixed-Use Complex · 25 Sept 2026

Hazy, 38°C
Carpenters 58Steel fixers 44MEP 31Helpers 70Total 203
Work done
  • Tower A core wall L11 poured
  • Podium waterproofing 60%
Rebar delivery PO-8812 short by 22 ton
Equipment: 2 × tower cranes, Concrete pump, Hoist H-1Visitors: Client PM site walk9 photos · Site Engineer — Marina

KIZAD Logistics Warehouse · 24 Sept 2026

Sunny, 41°C
Steel erectors 20Cladding 16MEP 22Helpers 25Total 83
Work done
  • Cold room panels bay 4–6 installed
  • Loading dock levellers 12/18 fixed
Equipment: 50T mobile crane, 3 × scissor liftsVisitors: Civil Defence pre-inspection11 photos · Site Engineer — KIZAD

Sharjah Community Health Clinic · 24 Sept 2026

Sunny, 37°C
Masons 14MEP 18Painters 8Helpers 12Total 52
Work done
  • Isolation room partitions set-out
  • Medical gas first fix 40%
Awaiting approval of lead-lined door submittal
Equipment: Mini excavator, Mobile scaffoldVisitors: —6 photos · Site Engineer — Clinic