Projects
AJM-2024-005
Ajman Industrial Workshop
Gulf Steel Fabricators · Ajman Industrial Area 2
CompletedLow
Contract value
AED 14.6M
Budget
AED 12.7M
Actual cost
AED 12.3M
97% spent
Forecast
AED 12.3M
-3.1% vs budget
Progress
100%
Planned 100%
Completion
15 Mar 2025
Started 01 Feb 2024
Project summary
Steel fabrication workshop with 20T overhead cranes and admin block.
Actual 100%Planned 100%
Timeline
0 tasks · 0 delayed
Team & client
- Project manager
- Daniel Fernandes
- Project type
- Industrial
- Client
- Gulf Steel Fabricators
- Client contact
- Ravi Menon
- Location
- Ajman Industrial Area 2